AH-64E · Army · Boeing
Explore AH-64E interactively →
Download 1-page brief (PDF)
Source: GAO-13-294SP, AH-64E Apache Remanufacture assessment p.41 — Program Performance table, constant FY2013 $M: first full estimate 08/2006 $7,453.4M / 602 aircraft vs latest 08/2012 $11,789.2M / 639; PAUC +49.0%; cycle 79 → 88 months; IOC 11/2013. Later GAO tables: +81.1% (GAO-15-342SP, FY15$), +78.8% (GAO-19-336SP, FY19$).
Drift — an independent project by Aous Abdo · Analytica DSS, built from public GAO, CRS and DoD sources. Cost growth has many causes; a larger number is not by itself evidence of mismanagement. How this is built · Explore the data →