ARH-70 · Army · Bell · cancelled
Explore ARH-70 interactively →
Download 1-page brief (PDF)
Source: GAO-08-467SP, ARH profile pp.43-44 — constant FY2008 $M: first full estimate 07/2005 $3,407.7M / 368 helicopters vs 08/2007 $5,728.3M / 512; unit cost +20.8%; cycle 47 → 72 months. GAO-09-326SP p.152: after a critical Nunn-McCurdy breach (notified Jul 2008), USD(AT&L) declined to certify and DoD ended the program Oct 2008.