F-35 Lightning II

F-35 · DoD · Lockheed Martin

+108% $233.0B (2001) → $485.2B (2023)
F-35 Lightning II: cost trajectory from $233.0B in 2001 to $485.2B in 2023, +108% growth. Explore F-35 interactively → Download 1-page brief (PDF)
Baseline
$233.0B (2001)
Current estimate
$485.2B (2023)
Cost growth
+108%
Units
2852 → 2470
Quantity change
−13%
Unit-cost change
+140%
IOC
2012 (planned) → 2015 (USMC)
Schedule slip
+3 yr
Cost basis
TY
Confidence
high · reconciled
+108% (then-year). Quantity cut 2,852 → 2,470, so per-unit growth exceeds total growth. It breached Nunn-McCurdy (a 2010 critical breach). Excludes ~$1.58T life-cycle O&S.

Documented events

Source: GAO-25-107632 (Sep 2025), Table 1; Dec 2023 F-35 Modernized SAR. All then-year $. Reaffirmed ~$485B in GAO-26-108457 (Jul 2026) — no newer estimate filed.