Land Warrior · Army · General Dynamics · cancelled
Explore Land Warrior interactively →
Download 1-page brief (PDF)
Source: GAO-07-406SP, Land Warrior profile pp.99-100 — constant FY2007 $M: first full estimate 02/2003 $2,692.8M / 15,985 systems vs 08/2006 $3,504.0M / 24,849; unit cost −16.3%; cancellation stated in the same profile. Interim plan swung to 85,412 systems / $9,274.6M (GAO-06-391, FY2006$ — different basis, not mixed in). Program start Aug 1994; cycle 145 → 175 months.
Drift — an independent project by Aous Abdo · Analytica DSS, built from public GAO, CRS and DoD sources. Cost growth has many causes; a larger number is not by itself evidence of mismanagement. How this is built · Explore the data →