EA-18G · Navy · Boeing
Explore EA-18G interactively →
Download 1-page brief (PDF)
Source: EA-18G SAR Dec 2015 (16-F-0402 DOC 51), SAR Baseline History p.26 — then-year $M: Nov 2003 development estimate $8,421.6M / 90 aircraft → Jul 2007 production estimate $8,636.4M / 84 → current $15,672.4M / 160; PAUC $93.6M → $98.0M TY (+4.7%). BY2004$ pair pp.12-13: $7,530.8M / 84 → $13,186.9M / 160. No Nunn-McCurdy breaches, either baseline; cost variance decomposition attributes the growth to quantity (+$4.2B BY2004$).
Drift — an independent project by Aous Abdo · Analytica DSS, built from public GAO, CRS and DoD sources. Cost growth has many causes; a larger number is not by itself evidence of mismanagement. How this is built · Explore the data →