G/ATOR · Navy · Northrop Grumman
Explore G/ATOR interactively →
Download 1-page brief (PDF)
Source: GAO-17-333SP, G/ATOR profile p.99 — constant FY2017 $M: first full estimate 08/2005 $1,590.1M / 64 radars vs 12/2015 $2,818.4M / 45; unit cost +152.1%; cycle 66 → 155 months; Blocks 1+2 at both ends. GAO-19-336SP p.107 corroborates (development +194.4%, FY2019$). USMC program, Navy-led.
Drift — an independent project by Aous Abdo · Analytica DSS, built from public GAO, CRS and DoD sources. Cost growth has many causes; a larger number is not by itself evidence of mismanagement. How this is built · Explore the data →