RQ-4 · Air Force · Northrop Grumman · truncated
Explore RQ-4 interactively →
Download 1-page brief (PDF)
Source: GAO-13-294SP, RQ-4A/B assessment pp.113-114 — Program Performance table, constant FY2013 $M: first full estimate 03/2001 $5,548.9M / 63 aircraft vs latest 08/2012 $10,021.0M / 45; PAUC +152.8%; cycle 55 → 125 months. GAO-12-400SP pp.77-78: April 2011 critical Nunn-McCurdy breach reported to Congress; restructure 77 → 55; Jan 2012 Block 30 termination plan.