Tactical Tomahawk (Block IV)

Tomahawk · Navy · Raytheon (RTX)

+48% $3.0B (2000) → $4.4B (2013)
Tactical Tomahawk (Block IV): cost trajectory from $3.0B in 2000 to $4.4B in 2013, +48% growth. Explore Tomahawk interactively → Download 1-page brief (PDF)
Baseline
$3.0B (2000)
Current estimate
$4.4B (2013)
Cost growth
+48%
Units
2790 → 3800
Quantity change
+36%
Unit-cost change
+8%
IOC
2004 → 2004
Schedule slip
0 yr
Cost basis
BY
Confidence
high · reconciled
+48% (BY1999) — but almost entirely QUANTITY: the buy grew 2,790 → 3,800 missiles while per-missile cost stayed flat (PAUC ~$1.37M). Buy-more growth, not an overrun.

Source: TACTOM Dec 2013 SAR (DTIC ADA614910): $2.98B/2,790 → $4.40B/3,800, BY1999$.