B-52 CERP · Air Force · Boeing / Rolls-Royce
Explore B-52 CERP interactively →
Download 1-page brief (PDF)
Source: B-52J CERP MSAR Dec 2023: $8,959.0M (FY22-NDAA-directed administrative baseline = AFCAA estimate of Mar 2020) → $9,512.4M, both BY2019$ (TY $12,961.6M); Dec 2022 SAR confirms the prior pair. GAO-25-107569 pp.65-66; GAO-26-108457 pp.79-80. STILL PRE-MILESTONE-B — no APB as of Jul 2026 (MS B planned 3Q 2026, held by an affordability study).
Drift — an independent project by Aous Abdo · Analytica DSS, built from public GAO, CRS and DoD sources. Cost growth has many causes; a larger number is not by itself evidence of mismanagement. How this is built · Explore the data →