Army IAMD (IBCS)

IBCS · Army · Northrop Grumman

+19% $4.9B (2009) → $5.8B (2015)
Army IAMD (IBCS): cost trajectory from $4.9B in 2009 to $5.8B in 2015, +19% growth. Explore IBCS interactively → Download 1-page brief (PDF)
Baseline
$4.9B (2009)
Current estimate
$5.8B (2015)
Cost growth
+19%
Units
296 → 447
Quantity change
+51%
Unit-cost change
−21%
IOC
2016 (planned) → 2023
Schedule slip
+7 yr
Cost basis
BY
Confidence
medium · reconciled
+19% real (BY2009), driven by a quantity increase 296 → 447 at roughly flat unit cost. Both endpoints are the Dec 2015 SAR baseline vs. current estimate in constant BY2009 dollars — an earlier row mistakenly paired the BY2009 and then-year versions of the same estimate, manufacturing +21% out of inflation. (Later restructured onto BY2023, ~$12.1B, different unit definition — not comparable.)

Source: Army IAMD Dec 2015 SAR (DTIC AD1019460), Cost Summary (BY2009): baseline $4,856.6M / 296 → current estimate $5,788.7M / 447, both constant BY2009 dollars. Reconciled directly to the primary SAR PDF. (Later restructured onto BY2023 — not comparable.)

Drift — an independent project by Aous Abdo, built from public GAO, CRS and DoD sources. Cost growth has many causes; a larger number is not by itself evidence of mismanagement. How this is built · Explore the data →