CH-47F Block II Chinook

CH-47F · Army · Boeing

−10% $16.2B (2018) → $14.6B (2024)
CH-47F Block II Chinook: cost trajectory from $16.2B in 2018 to $14.6B in 2024, −10% growth. Explore CH-47F interactively → Download 1-page brief (PDF)
Baseline
$16.2B (2018)
Current estimate
$14.6B (2024)
Cost growth
−10%
Units
542 → 542
Quantity change
0%
Unit-cost change
−10%
IOC
TBD → TBD
Schedule slip
Cost basis
BY
Confidence
high · reconciled
A genuine cost DECREASE, stated in the SARs: the Feb 2018 baseline $16.2B (BY2017) rose to $17.4B by Dec 2018, then fell steadily to $14.6B in the Dec 2023 MSAR (−10%, quantity unchanged at 542 = 3 development + 539 procurement, incl. common production costs of 69 MH-47G) — procurement-driven, GAO’s second-largest decrease. After GAO’s Jan-2025 cutoff the Army cut the buy to 432 Block II + 69 MH-47G and moved the program to the MTA pathway (Sept 2025); no stated cost pair exists for that structure yet, so this row keeps the 542-aircraft basis.

Source: CH-47F Block II SAR Dec 2018 p.35 (Feb 1 2018 APB Development Estimate, BY2017$) + Dec 2023 MSAR pp.14,16 (PB2025 current estimate, BY2017$), qty 542 both sides; interim points from the Dec 2019 SAR summary tables and Dec 2021 SAR p.5. GAO-25-107569 p.91’s chart bars are these figures converted to FY2025$.